Philippines launches US$0.23 per kWh solar FIT
 
The Energy Regulatory Commission (ERC), on July 27, 2012, approved the initial Feed-in Tariffs (FITs) that shall apply to generation from renewable energy (RE) sources, particularly, Run-of-River Hydro, Biomass, Wind, and Solar.
Send to a friend

The Energy Regulatory Commission (ERC), on July 27, 2012, approved the initial Feed-in Tariffs (FITs) that shall apply to generation from renewable energy (RE) sources, particularly, Run-of-River Hydro, Biomass, Wind, and Solar, as follows:

APPROVED FITS (PhP/kWh)
HYDRO                  5.90
BIOMASS               6.63
WIND                      8.53
SOLAR                   9.68
 
The ERC, however, deferred fixing the FIT for Ocean Thermal Energy Conversion (OTEC) Resource for further study and data gathering.

The decision came after a series of public hearings ending in March this year, on the petition of the National Renewable Energy Board (NREB) for the setting of the FITs.

In fixing the FITs, the ERC accepted the methodology used by NREB in calculating its proposed FITs, which takes into account, among others, the cost of constructing and operating the representative plants for each RE technology, the generation output or capacity factors of these plants, and the reasonable return on investment to be allowed the developers of these plants.

The ERC arrived at FITs substantially lower than NREB's proposed FITs for Wind and Solar after it updated the construction costs of the representative plants for these technologies to reflect the downward market trend of the costs of putting up these plants. It also adopted higher capacity factors for these plants to ensure that only the more efficient plants will enjoy the FIT incentive.

For all the RE technologies, the ERC revised other project costs such as those for the switchyard and transformers, transmission interconnection cost and access/service road cost using the same benchmarks it had employed in approving similar projects of the regulated utilities.

Section 7 of the Renewable Energy Act of 2008 mandates, among others, the setting of the FITs to apply to wind, solar, run-of-river hydro, biomass, and ocean RE resources. Under the FIT system, the eligible RE developers will be paid the FITs applicable to them for the energy they feed into the grid. The FITs are subject to degression to encourage the developers to invest at the initial stage and hasten deployment of renewable energy and also to avoid substantial windfall from being enjoyed by developers especially in the technologies where significant cost reductions are expected in the future.

The approved FITs shall also be subject to review and readjustment by the ERC after the initial FIT implementation of 3 years or when the installation targets for each technology as set by the Department of Energy shall have already been met.

 

 
More PHOTOVOLTAICS news

Apr 15th
Apr 11th
Apr 10th
Apr 8th
Apr 8th
 
©2007 Yole Developpement All rights reserved                  Disclaimer | Legal notice | To advertise
Yole Développement: Le Quartz, 75 cours Emile Zola, 69100 Villeurbanne, France. TEL: (33) 472 83 01 80 FAX: (33) 472 83 01 83 E-Mail: info @yole.fr